Isabella Lake Dam
Project Details
Location
CaliforniaDelivery method
Bid-BuildRole
Joint Venture LeadClient
U.S. Army Corps of EngineersValue
$336MCompletion date
2023Project Overview
The Isabella Lake Dam Safety Modification project, led by the FlatironDragados and Sukut joint venture, enhanced the safety and operational capacity of the Isabella Lake dams for the U.S. Army Corps of Engineers.
In 2006, a USACE study found the dam vulnerable to three potential failure modes: overtopping, seepage and seismic damage, naming Isabella the “most dangerous dam in America.” The project addressed each of these issues.
Key elements included:
- Main and auxiliary dams raised by 16 feet
- Construction of 300-foot-wide emergency spillway with 28-foot-high labyrinth weir
- Existing spillway reconstructed; new emergency spillway fortified with 35-foot-long anchor bolts
- Filtering and drainage systems enhanced
The project, completed in 2023, ensures long-term flood-risk management and reinforces the dam’s structural integrity, benefitting the 300,000 people living and working downstream.




Awards
- 2023 Dam Safety Award, National Rehabilitation Project of the Year, Association of State Dam Safety Officials
- 2023 CMAA Project Achievement Award, Environmental: Construction Value Greater than $50 Million, Construction Management Association of America
Key Stats
Careers
Great projects start with great people. At FlatironDragados, we’re more than just a team – we’re a community of innovators, problem solvers and builders.
Whether you are just starting your career or bringing years of experience, you’ll find a home here. Transform your career with us.
Latest News
Loading...